Gurgaon new roads, metro, pod n RRTS status
Gurgaon Various Infra Projects News/Status
Please find below the useful links on the news/status of various Gurgaon road/ metro/ rail projects
New Road between Gurgaon and Vasant Kunj
KMP Expressway Progress Hindi Article
Gurgaon-Faridabad Road and Ballabhgarh-Sohna Road Widening
New-flyover-underpasses-cybercity
Gurgaon NPR & SPR (Northern Periphery Road & Southern Periphery Road)
Gurgaon NPR project plots to be offered in compensation
Eastern Peripheral Expressway hurdles cleared
Gurgaon Private Metro/ Rapid Ransit Sstem (RRTS) /Pod Taxi/Infra Projects
Gurgaon Private Metro (Rapid Metro Rail Gurgaon)
Gurgaon Manesar Corridor infrastructure
NCR orbital trains along peripheral expressway
Categories: Gurgaon, NCR Transportation Tags: eastern peripheral expresway, gurgaon faridabad road widening, gurgaon metro, gurgaon new roads, gurgaon NPR, gurgaon pod taxi, gurgaon private metro, gurgaon spr, gurgaon vasant kunj new road, KMP expressway, NCR RRTS
Gurgaon NPR- Inching Closer
No Progress Road: NPR to miss second deadline
HT Correspondent, Hindustan Times
Gurgaon, December 03, 2012
Eight months after it missed its first deadline, the much-hyped Rs. 57 crore Northern Peripheral Road (NPR) project is still struggling to reach the finish line even as the second deadline looms round the corner. The 18-km-long road, also known as Dwarka Expressway, is bound to miss the
December 31 completion deadline — thanks to the lackadaisical attitude of the Haryana Urban Development Authority (Huda).
The 150-metre-wide road will connect Dwarka in Delhi and Kherki Daula on NH-8.
Of the 18-km stretch, the bituminous work is complete hardly on eight km area. Moreover, a four-km stretch is entangled in a legal dispute.
"We still have 28 days and we hope to complete at least five km. I have asked the contractor to speed up the work and complete the stretch by end of the month," said Pankaj Kumra, chief engineer, Huda, the custodian authority of the project.
When questioned about the reason for the delay, the chief engineer said, "The contractors are facing law-and-order problems on the NPR, mainly on the portion under litigation. The workers are having difficulty as many houses and establishments have not been removed for the work.”
The delay has shattered the dreams of tens of thousands of buyers and builders whose money is invested in hundreds of projects coming up along the NPR. The project was awarded to JSR Construction Pvt Ltd and Indiabulls Construction Limited on April 1, 2011 and its first deadline was March 31, 2012.